HAREESH VILLA @ CHALAKUDY
Friday 19 August 2016
Plastering Work
Thursday 10 March 2016
Plastering Progressing
Wednesday 10 February 2016
Main Roof Work Progressing 08-02-2016
Thursday 29 October 2015
Lintel Work Progressing 28-10-2015
Thursday 17 September 2015
Brick Work Progressing 16-09-2015
Thursday 10 September 2015
Basement Work 09-09-2015
Wednesday 15 July 2015
Foundation Stone Laying 13-07-2015